Author Topic: Cruck Frame Raising
Ken Hume
Administrator
Posts: 423
Permalink
Post Cruck Frame Raising
on: January 1, 2018, 11:02
Quote

The cruck frame was raised on 10 November 2017 by the OWG trustees and fellows.

Work then proceeded to stabilise the frame by fitting wall plates to the sidewalls enabling the removal of temporary sidewall bracing and then fitting a single piece (30ft +) Douglas Fir ridge hewed to form a 16 sided (round) section.

Hewn rafter stock was then used to span between the cruck mantles (tie beams) to support a temporary upper plank floor to enable roof work to proceed.

Image

Single piece (30ft +) Douglas Fir purlins were then hewed

Image

and raised into position to sit (double lap jointed) on the backs of the principal (packer) rafters.

Image

A tarpaulin was stretched across the ridge to form a temporary roof to help keep the raised frame dry.

Ken Hume

Pages: [1]
Mingle Forum by cartpauj
Version: 1.0.34 ; Page loaded in: 0.021 seconds.

Events Calendar

January  2018
Mon Tue Wed Thu Fri Sat Sun
   
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31  

Training

Download our .pdf here.

Up Coming Events

Annual General Meeting Saturday 15th September 2012 will be held at Wytham Wood, please contact us for details.